River notice 03-22

Navigation information - barge at Tennants Textiles

Notice is hereby given that a large barge will be working alongside the wall at Tennants Textiles from 22 February for a period of two weeks. The barge is carrying out ground investigations in connection with the Belfast Tidal Project.  The barges work area is as per the enclosed sketch and it will be moored in this area at night. The barge will be marked by buoys and will be lit during the hours of darkness.

River users are asked to exercise due caution around the barge and to give it a wide berth.

The River Warden’s boat will be on duty to ensure that river users comply with the River Lagan Tidal Navigation and General Bye-Laws (NI) 2007 applicable to this Notice.

Peter Gallagher
River Manager
Belfast Regeneration Directorate
4th Floor, NINE Lanyon Place
Belfast
BT1 3LP

 

 